The lifespan of equipment and its operational safety depend directly on regular maintenance performed by qualified personnel. The more detailed the maintenance plan, the longer the machine will operate without failure, delivering maximum economic benefits.


Initial maintenance includes the following stages:

Hydro Accumulator: Check the nitrogen pressure. During the first week of operation, if the pressure drops by more than 5 bar, the machine must be stopped and the system’s tightness inspected. Pressure monitoring in the hydro accumulator should follow a scheduled plan: the first check one week after start-up, the second after one month of continuous operation, and every three months thereafter.
Hydraulic Oil: After the first 500 hours of operation, changing the oil is mandatory. Subsequently, its condition should be checked annually. If the oil no longer meets standards, it must be filtered or replaced.

DC300_AI看图.jpgHydraulic tank: Before the first filling with oil, the hydraulic tank must be thoroughly rinsed. Subsequently, rinsing is required with each oil change.

Suction filter: After the first 500 hours of operation, it is essential to clean the filter. Thereafter, cleaning should be carried out every six months.

Topic: Maintenance of Machine Components

2. Maintenance of the Main Components of the Machine

2.1 Maintenance of External Parts of the Pressure Die Casting Machine

2.2 Maintenance of the Hydraulic System

2.3 Maintenance of the Electrical System

2.4 Maintenance of the Mold Closing Unit

2.5 Maintenance of the Injection Unit

2.6 Maintenance of the Lubrication System

2.7 Maintenance of the Cooling System

2.8 Maintenance of the Heat Treatment System

3.Schedule of Regular Maintenance and Inspections